How to move P&ID's from one project to another?
Since Relationship Manager is not an option for P&ID drawings the option available is to Create an Exchange of the Drawing and Import into the secondary project.
Solution: Use the Create Exchange Drawing function in the P&ID-Tools > Import Export Utility.
1. Open the drawing in Project A. Create Exchange Drawing (P&ID-Tools > Import Export Utility.)
2. Open Project B in Document Manager. Right Click and select Import > Select the Exchange Drawing.
3. Open the Drawing and import the tags using Defined Tags. The drawing and data are now copied into the new project.
____________________
See Also
External Links
Bentley Technical Support KnowledgeBase
Comments or Corrections?
Bentley's Technical Support Group requests that you please confine any comments you have on this Wiki entry to this "Comments or Corrections?" section. THANK YOU!