Document Information
Document Type: TechNote
Product(s): ProjectWise and Project Administrator
Version(s): 08.11.09.140
Original Author: Bentley Technical Support Group
Overview
Sometimes during ProjectWise Integration with Project Administrator the dialog that is used for the integration will be greyed out as shown below:
Cause/Solution:
1. Check the install order of the Bentley Applications. ProjectWise must be installed before any AutoPLANT applications. This will allow AutoPLANT upon installation to make the correct ProjectWise connections.
2. Make sure the C:\Program Files (x86)\Bentley\ProjectWise\Bin\Pwintutilsv8i.dll exist.
3. The project must be a Central Mode Project. Distributed Mode Projects will not sync with ProjectWise.