If the Project Type Conversion Wizard* is not installed how do I manually convert my Distributed Project Mode to the Central Mode?
* The Project Type Conversion Wizard is a tool found in the Tools menu of Project Administrator. However, the Project Type Conversion Wizard is only installed with Plant Design Workgroup.
Please follow the steps outlined below to convert the project:
1. Make sure everyone is out of the project. Backup the project.
2. Browse to the Data Repository for the project. This will be the Projdata.mdb or SQL Server, Oracle Database.
3. Open the Properties3d table and modify the DBACCESSTYPE Value from 1 to 2 as outlined below:
Distributed Project Type value is 1. The Central Project Type value is 2.